Project Case Study: Kennedy Health Cherry Hill

The curtain wall was completed in March; photo © Amanda Weko
Photo source
© Amanda Weko

Date: 18 July 2017

Five different curtain walls clad a new medical office building.

 

AGI Glazier

Guthrie Glass & Mirror, Inc.

Egg Harbor Township, N.J.

Team

Architect: EwingCole

Contractor: Norwood Construction

Curtain wall manufacturer: Kawneer

Subcontractors involved with the

curtain wall construction:

Steel: Southern NJ Steel

Blueskin system: EDA Contractors

Carpentry: Hagan Construction

Seals: Crawford Caulking

Completion

May 2017

rendering (courtesy Norwood Construction and EwingCole)
Courtesy Norwood Construction and EwingCole

 

$250 MILLION UPDATE

Kennedy Health has maintained Cherry Hill, N.J.’s only hospital since 1961. Today, the hospital campus is undergoing a massive $250 million update to coincide with a rebranding and merger with Jefferson Health.

Phase I of the expansion project features a new 700-car parking garage, a 102,000-sf outpatient medical office building, and a dramatically glazed connector atrium that links the existing hospital building with the new structure.

Construction progress images (courtesy Guthrie Glass)
Construction progress image | courtesy Guthrie Glass

 

TEAMWORK

The project began in 2015 with architectural design and structural engineering by EwingCole. Glass figures prominently into the aesthetic – five different types of curtain wall are included on the project with three different types in the lobby alone.

EwingCole and general contractor Norwood Construction called on Guthrie Glass & Mirror to help execute the complicated glazing solution.

Guthrie Glass is a woman-owned commercial glazing contractor based in South Jersey. President Lynn Guthrie and her team are known for performing challenging work and were up to the task.

“It was an extremely difficult job,” Guthrie said. “We conducted many meetings in advance and worked with EwingCole, Norwood, and the subcontractors to stay on top of issues, come up with solutions, and keep the project moving.”

She credits father and son Tom and Tommy Domanick, Guthrie Glass site superintendent and general foreman, with working daily to ensure effective communication and coordination, particularly critical on a tight site with many crews working in limited space.

Norwood superintendent Ryan Spots agreed the Guthrie Glass teamwork and organization made the project possible. “Guthrie did a fantastic job,” Spots said. “This was one of the most complex curtain wall systems I’ve ever come into contact with, and Lynn and her team were great from conception to installation. They worked through issues and details Kawneer had never encountered before.”

Construction progress images | courtesy Guthrie Glass
Construction progress image | courtesy Guthrie Glass

 

VARIETY OF GLAZING

The lobby contains 11,000 sf of Kawneer Clearwall four-sided structural silicone glazed (SSG) and 1600 SSG captured curtain wall featuring Viracon glass with different shaped and sized frits.

“Every piece of glass had a different etching, shape, or design,” explained Guthrie, making installation significantly more challenging to ensure each piece went into the correct position.

The 1600 walls are splayed with sloped walls, extended cover caps with fins, and extended wing walls, some of which spanned as much as 16 feet from the interior structural supports.

Guthrie general foreman Tommy Domanick explained carrying the cantilevers for the wing walls was a major challenge: “We needed to integrate structural steel into the curtain wall’s mullion system.”

Guthrie bench-fabricated the steel into the curtain wall system on the ground. Once the sections were in position on the building, subcontractor Southern NJ Steel performed the weld connections.

“It was a team effort to make it all look seamless.”

Vapor barrier details were coordinated closely with EDA Contractors, Hagan Construction, and Crawford Caulking.

Incorporating the motorized glass vents of the lobby atrium presented an additional challenge, as each had to be connected to the building’s smoke evacuation system and coordinated with automatic doors and other systems.

Construction progress image | courtesy Guthrie Glass
Construction progress image | courtesy Guthrie Glass

 

ADDITIONAL SCOPE

Guthrie Glass installed glazing throughout the project, including Kawneer ribbon windows with glass vents and vertical sunshades on the outpatient building.

All five interior floors of the atrium are wrapped with 5/8-inch low-iron glass railings with components from J.E. Berkowitz. Back-painted interior glass accent walls feature McGrory Glass. Dozens of glass sliding and swing doors with continuous sidelites round out the package.

www.theagi.org

600450 Project Case Study: Kennedy Health Cherry Hill glassonweb.com

Others also read

Victoria Regina Tower in Brussels is embracing a sustainable future with the help of Şişecam’s high-performance solar control glass.
PRPM Architekten’s design connects old and new Innsbruck, with OKALUX KAPILUX T providing diffuse daylight and thermal comfort.
The Face2Face Campus in Katowice features Glas Trösch’s high-performance glass, combining design, comfort, and efficiency.
With SANCO ESI Sun and SANCO Plus Zero NG glazing by Glas Zange, the project combines sleek architectural design with outstanding solar control and thermal insulation, shaping a bright, energy-efficient future for the city.
Featuring OKALUX EVO insulating glass, the architecture invites nature in while ensuring optimal light, comfort, and energy performance.
With dynamic glazing by Scheuten Glas and a façade designed to perform as well as impress, the building blends visual impact with energy efficiency — redefining modern urban living.

Add new comment

From industry

2200 W. Salzburg Rd.
Auburn , MI 48611
United States

NEWS RELATED PRODUCTS

Diamon-Fusion International, Inc.
Kuraray Europe GmbH
Qingdao REXI Industries Co., Ltd
Kuraray Europe GmbH
Guardian Glass Europe
Rider Glass Company Limited