Four glass buildings mark a dynamic new workplace

Date: 15 February 2017
Source: www.theagi.org
Princeton Pike Campus
Photo source
Courtesy of Bristol-Myers Squibb

Date: 15 February 2017

Glass figures prominently into the design of Bristol-Myers Squibb's new Princeton Pike Campus.

AGI member National Glass & Metal Co., Inc., worked with the architectural team from Gensler and construction team from Torcon to design and install four different glazing systems on a very aggressive schedule.

 

AGI Glazier

National Glass & Metal Co., Inc.

Horsham, Pa.

Team

Architect: Gensler

General Contractor: Torcon, Inc.

Owner’s Representative: The Cadence Group

Building Envelope Consultant: Wiss Janney Elstner Associates, Inc.

Structural Engineer: Harmon Group, Inc.

Civil Engineer: Van Note-Harvey

MEP Engineer: AKF Engineers

Completion

Winter 2017

Two of the four buildings nearing completion; west atrium wall in background (all photos courtesy National Glass & Metal Co.,Inc.)
Two of the four buildings nearing completion; west atrium wall in background (all photos courtesy National Glass & Metal Co.,Inc.)

 

NEW CAMPUS

Bristol-Myers Squibb is a global biopharmaceutical company with a strong presence in central New Jersey. When the company planned to construct a new office campus for 2,500 employees in Lawrence Township, glass figured prominently into the design.

 

OPEN AND LIGHT

Architect Gensler developed an H-shaped configuration of four buildings connected by a central atrium. Entirely glass-clad, the complex emphasizes openness.

“Bristol-Myers Squibb wanted to take advantage of the 93 acres that surround the buildings and keep all spaces open to views and light,” said Project Architect Brad King, AIA.

He and Design Director Jeff Barber, AIA, prioritized the configuration based on collaboration; it takes less than five minutes for an employee to reach colleagues on the opposite side of the structure.

The glass atrium stands as the centerpiece of the 650,000-squarefoot facility. Four-story glass walls and a clerestory fill the interior with natural light. National Glass & Metal Co., Inc., was instrumental to both the design and execution of the atrium and the project’s comprehensive glazing scope of work.

“The atrium was different and unique. We had a vision for keeping it open but needed National’s design-build expertise to get it right,” explained King. National helped Gensler achieve the aesthetic. “It was a very positive experience. National handled the systems well and were very helpful in the process, added King.

Princeton Pike Campus

 

TEAM EFFORT

National relied on several key players to execute the project quickly and efficiently: Lead Foreman Brendan Kearney, Senior Project Manager John Norwood, and Assistant Project Manager/ Project Engineer Meghal Patel were supported by Project Coordinator Sabrina Parsons. “It was absolutely a team effort,” said National President Joseph E. Clabbers.

 

FOUR SYSTEMS

National designed and employed four different glazing systems: a butt-glazed unitized system, a captured unitized system, a captured curtain wall system, and a structurally glazed cassette system. Viracon, Inc., provided the glass while United Architectural Metals supplied the unitized curtain walls.

The cassette system uses insulated glass units structurally glazed to a framework of thin metal hooks applied to four edges. The top and bottom hooks affix to hooks on a grid framework of tubular aluminum applied to the building steel.

The shop-glazed system was used on the north and south entry walls and east and west atrium walls. National developed a screw-spline construction system for the nonunitized curtain walls used at the ground level and at recessed areas.

The method used ladder frames built in the shop. These have vertical mullions split in two that create a reveal on the back of the mullion and closely match the reveal on the back of the unitized system.

This ensured harmony when the two different systems were installed side by side, while allowing National to do all gasketing and sealant work in the shop.

Princeton Pike Campus

 

SCHEDULE & EFFICIENCY

“It was a very aggressive schedule from the outset,” explained Clabbers. National had roughly six months from October to April to fully enclose the building. “Since it was winter, we tried to minimize the weather impact to our work.”

To complicate the glazing, the buildings do not include any true right angles. Each angle is subtly off from 90 degrees, and many of the facade recesses were accented with cantilevered glass fins.

This created logistical and layout challenges to ensure the unitized glazing system units fit perfectly.

“We did extensive layout and planning to really make the project a success,” explained Clabbers. “We knew we had to hit the ground running, and we were able to do that.”

National fabricated and pre-assembled components to the greatest extent possible in the shop, where the controlled environment enables optimum quality control.

According to Patel, the unitized systems resulted in a 50 percent time savings – with completion in roughly eight months vs. a year and a half in the field with all stick-built construction.

600450 Four glass buildings mark a dynamic new workplace glassonweb.com

Others also read

Recognised for regional commitment
Vitro Architectural Glass is pleased to announce that its energy-efficient, low-embodied carbon glass is featured in eight award-winning projects recognized by the American Institute of Architects (AIA).
With the steady progress of the NorthGlass High-End Equipment Industrial Park project, the landmark R&D Center Building’s "Super Glass" curtain wall has been successfully installed.
OmniDecor glass adds elegance and modernity to Milano Prime’s luxury terminal at Malpensa Airport.
Mississippi’s first dedicated children’s hospital, the Sanderson Tower, combines advanced care and modern design with Vitro’s Solarban® 90 glass for a bright, welcoming space.
Birmingham revitalizes its Brutalist arena facade with a new curtain wall featuring Solarban® 72 Acuity® glass by Vitro Architectural Glass.

Add new comment

From industry

NEWS RELATED PRODUCTS

Guardian Glass Europe
Diamon-Fusion International, Inc.
Qingdao REXI Industries Co., Ltd
Guardian Glass Europe
Wenfrod Glass Processing Co. (Tempered Glass Factory Turkey)
Diamon-Fusion International, Inc.