Colorminium Project: 79 New Cavendish Street

Date: 11 February 2019
Source: colorminium.com
Colorminium Project: 79 New Cavendish Street
Photo source
colorminium.com

Date: 11 February 2019

Occupying a prominent corner plot and situated to the North of Regent Street, this existing building was converted into high end commercial office space.

 

Key Challenges

  • Replacement window package to rear existing openings with curved heads
  • Minimal sight-lines required to all glazed elements to the main elevations whilst maintaining acoustic and thermal performance
  • Sequencing with the stonework contractor to ensure weather and air seal lines are maintained.

79 New Cavendish Street

 

The Brief

Having gone through a number of design revisions to maximise the value for the client, the final commercial scheme was approved and construction is now complete.

Main contractor Osborne bought Colorminium on board with an early design order to assist in working up the detailing and ensuring that the buildability sequence and interfacing with the structure and stone was understood. Once the initial design work was complete, Colorminium went on to secure the contract to deliver the works.

 

 

Our Approach

The existing brick clad façade was stripped back to the primary structure line and new stone cladding installed over the column and slab lines. Punch hole elements were then installed into the opening giving full height apertures of glazing around the two primary elevations.

To the rear of the building, the existing façade was retained and all windows replaced. This involved a complex survey to rationalise all window types and bring some continuity and rhythm to the façade. At 5th floor, the existing structure rakes back in a slate clad mansard roof with replacement windows within the existing dormers.

At roof level, plant screens mask the air handling equipment from neighbouring properties whilst at ground floor level the stone openings are enlarged and infilled with curtain walling to give a broader frontage at street level. Access to the building is through a pure bronze main entrance doorset, also supplied by Colorminium.

79 New Cavendish Street

 

The Result

The window installation was completed in 2018 and fit out started straight away prior to the client taking possession.

Client: Harley Property Holdings

Architect:Squire & Partners

Contractor: Osborne

Quantity Surveyor: Jackson Coles

Sectors: Corporate and Commercial

GDV: £8,000,000

 

Project Scope

  • Curtain walling
  • Doors and windows
  • Pure Bronze main entrance
  • Architectural metalwork
  • Louvres and plant room screening
600450 Colorminium Project: 79 New Cavendish Street glassonweb.com

Others also read

On Wednesday 6th November, FIT Show organisers gathered a group of FIT Show stakeholders, with a focus on its visitor audience, to hold the first in a series of advisory board meetings.
The 25th Eurasia Window, 16th Eurasia Door, and 14th Eurasia Glass Fairs have officially opened their doors at the Tüyap Fair and Congress Center in located Istanbul, showcasing the latest products and technologies in the industry.
With the steady progress of the NorthGlass High-End Equipment Industrial Park project, the landmark R&D Center Building’s "Super Glass" curtain wall has been successfully installed.
The floorplan for FIT Show 2025 is filling up fast, with organisers reporting that they are on target to increase the size of the show by 30% since its May 2023 event.
Mississippi’s first dedicated children’s hospital, the Sanderson Tower, combines advanced care and modern design with Vitro’s Solarban® 90 glass for a bright, welcoming space.
Thermal Bridging Considerations at Interface Conditions, Key Strategies for Bird Friendly Glazing School Security coming soon

Add new comment

From industry

NEWS RELATED PRODUCTS

Kuraray Europe GmbH
Guardian Glass Europe
A+W Software GmbH