Portland Building Overclad Nears Completion

Portland Building Overclad Nears Completion
Photo source
www.bensonglobal.com

Date: 21 March 2019

Progress continues on the overclad of Michael Graves’ post modern icon, The Portland Building.

Benson’s Otay Mesa Assembly Facility completed the last of the 946 curtain wall units this month. Installation on the final two elevations continue with an estimated substantial completion date slated for Mid-April.

Project Manager Melissa Johnson and Field Superintendent Charlie Graham have worked closely with our client Howard S Wright, A Balfour Beatty Organization coordinating the various trades working on this complex site.

The Portland Building’s curtain wall installation close to completion
The Portland Building’s curtain wall installation close to completion
600450 Portland Building Overclad Nears Completion glassonweb.com

Others also read

FTF, Fenster Türen Freund, a renowned Bavarian window and door specialist, has elevated its office building with advanced SANCO glass solutions.
To complement this visionary architecture, the roof employs Okalux’s OKASOLAR S system.
Featuring a clinker brick façade and green accents, the building showcases Hoffmann Glas Peine’s SANCO glass solutions, which enhance its aesthetic while offering superior insulation and energy efficiency.
Createch harnesses SWISSDIVIDE I system for precision-engineered, light-filled office spaces.
STRATO® products shine in the new Rijeka museum exhibit.
Continued collaboration reaffirms Vitro’s commitment to the community and environmental protection

Add new comment

From industry

NEWS RELATED PRODUCTS

Diamon-Fusion International, Inc.
Qingdao REXI Industries Co., Ltd
Guardian Glass Europe
Wenfrod Glass Processing Co. (Tempered Glass Factory Turkey)
Guardian Glass Europe
Diamon-Fusion International, Inc.