Portland Building Overclad Nears Completion

Portland Building Overclad Nears Completion
Photo source
www.bensonglobal.com

Date: 21 March 2019

Progress continues on the overclad of Michael Graves’ post modern icon, The Portland Building.

Benson’s Otay Mesa Assembly Facility completed the last of the 946 curtain wall units this month. Installation on the final two elevations continue with an estimated substantial completion date slated for Mid-April.

Project Manager Melissa Johnson and Field Superintendent Charlie Graham have worked closely with our client Howard S Wright, A Balfour Beatty Organization coordinating the various trades working on this complex site.

The Portland Building’s curtain wall installation close to completion
The Portland Building’s curtain wall installation close to completion
600450 Portland Building Overclad Nears Completion glassonweb.com

Others also read

Kuraray interlayers play a pivotal role
Daylight meets design in the new Activo center, where OKAWOOD enhances comfort, energy efficiency, and well-being on the shores of Bremen’s Werdersee.
Discover how Glas Trösch glass solutions bring clarity, efficiency, and timeless design to the heart of Katowice’s urban landscape.
In Paris Saint-Denis, Tour Maestro redefines architecture with a visible steel frame and high-performance Glas Trösch glazing that merges clarity, safety, and acoustic comfort.
A recent project has witnessed the fusion of safety and art, with a breathtaking artwork transformed into an interior design partition.
Developed by Related Ross and designed by SOM, the project showcases Solarban® R77 Acuity® glass by Vitro, setting a new standard for modern office design.

Add new comment

From industry

NEWS RELATED PRODUCTS

Guardian Glass Europe
Rider Glass Company Limited
Guardian Glass Europe
Qingdao REXI Industries Co., Ltd