Portland Building Overclad Nears Completion

Portland Building Overclad Nears Completion
Photo source
www.bensonglobal.com

Date: 21 March 2019

Progress continues on the overclad of Michael Graves’ post modern icon, The Portland Building.

Benson’s Otay Mesa Assembly Facility completed the last of the 946 curtain wall units this month. Installation on the final two elevations continue with an estimated substantial completion date slated for Mid-April.

Project Manager Melissa Johnson and Field Superintendent Charlie Graham have worked closely with our client Howard S Wright, A Balfour Beatty Organization coordinating the various trades working on this complex site.

The Portland Building’s curtain wall installation close to completion
The Portland Building’s curtain wall installation close to completion
600450 Portland Building Overclad Nears Completion glassonweb.com

Others also read

NorthGlass showcased its innovation in architectural glass at CTBUH 2025, demonstrating how cutting-edge technology and design push the boundaries of high-rise sustainability and aesthetics.
DFI is proud to announce the successful completion of the skylight insulated glass units at The Avenues – Riyadh, a landmark development designed to become the largest commercial mall in the Middle East.
Vitro Architectural Glass is marking a landmark year as several of its most influential Solarban® products reach major performance and innovation milestones.
When designing a façade today, a number of complex requirements must be considered: energy performance, low carbon footprint, comfort, durability, recyclability, aesthetics, cost effectiveness, etc.
Vitro’s Solarban® 72 Acuity® and Solarban® 90 glass help create a bark-inspired façade for UC San Diego’s Pepper Canyon West student housing.
Extreme Curves. 9 meters high, one meter in diameter, and millimeter precision

Add new comment

From industry

NEWS RELATED PRODUCTS

Guardian Glass Europe
Guardian Glass Europe
Qingdao REXI Industries Co., Ltd