Installation balustrades Moreelsebrug

Date: 10 June 2016

Since last week Octatube has started with the second installation sequence of the balustrades at the Moreelsebrug (formerly known as the Rabobrug).

The total length of the structurally glazed balustrades is approximately one kilometer. 



The bridge is 275 meters long and 10 meters wide. As yet there are no staircases to the platforms of Utrecht Central Station, but the design has allowed for additional stairs to be added in the future.

The first parts of the bridge have been transported to the building site by the end of last year and now half of the structure has been realised. The programme and installation works above the railway is complicated, and a lot of factors and adjacent projects have to be taken into account.















Completion of the bridge is scheduled for the end of this year.



Picture courtesy: cu2030.nl & Cepezed

600450 Installation balustrades Moreelsebrug glassonweb.com

Others also read

Redefine elegance in entrances, lobbies, and vestibules now
The new 14-story Hilton at Nashville International Airport combines innovative glazing solutions with precision engineering to deliver a striking, high-performance hotel.
(W)rapper is an impressive new office building showcasing contemporary architecture that aligns with the latest advancements in sustainable design.
Recognised for regional commitment
Vitro Architectural Glass is pleased to announce that its energy-efficient, low-embodied carbon glass is featured in eight award-winning projects recognized by the American Institute of Architects (AIA).

Add new comment

From industry

2200 W. Salzburg Rd.
Auburn , MI 48611
United States

NEWS RELATED PRODUCTS

Wenfrod Glass Processing Co. (Tempered Glass Factory Turkey)
Rider Glass Company Limited
Rider Glass Company Limited
Glas Trösch Holding AG