Advancing Electric Melting: GMIC’s DOE Grant Progress Update

Date: 25 February 2025
Source: gmic.org
The Cold-Top furnace set up in the temporary space at University of Toledo
Photo source
The Cold-Top furnace set up in the temporary space at University of Toledo | Photo: gmic.org

Date: 25 February 2025

GMIC advances electric melting research with a $3M DOE grant to cut glass production emissions by 85%+. Key progress: Cold-Top Furnace setup, successful tests, and glass formulation refinements.

Last year, GMIC was awarded a three-year, $3 million grant from the Department of Energy to research advanced electric melting to decarbonize commercial glass.

The objective of the project is to demonstrate melting processes which reduce scope-1 greenhouse gas emissions by 85+% for large volume, commercial glass production. The focus will be on overcoming three barriers which have hindered adoption of all-electric glass furnaces:

  • Production of dark/reduced colored glasses (e.g. amber)
  • Improve quality of clear glass
  • Furnace lifetime

The project launched in the last quarter of 2024, and accomplishments last quarter included:

  • Establishing the project lab and modeling capabilities
  • Setting up the Cold-Top Melting Furnace
  • Testing the pelletizing set up
  • Completing the CFD grid of the Cold-Top furnace
  • Establishing the future workflow plans

In addition, the team established base line recipes for the amber and flint tests. These recipes were chosen to represent real industrial glass melt formulas and be consistent across project members conducting tests in the CelSian lab, the PNNL lab, and through CFD modeling. Industrial-grade raw materials and post-consumer flint cullet were obtained from industrial steering committee partner Gallo Glass to maintain consistency with real-world industrial processes. Internal flint cullet was also obtained from a separate glass plant because of ease of acquisition.

For the quarter, five successful cold-top experiments were run on the Cold-Top furnace:

  • Container batch containing 30% post-consumer flint cullet at 2.0 ton/m 2 /day
  • Container batch containing 30% internal flint cullet at 2.0 ton/m 2 /day
  • Container batch containing 30% internal flint cullet at 1.75 ton/m 2 /day
  • Container batch containing 70% internal flint cullet at 2.0 ton/m 2 /day
  • 100% internal flint cullet at 2.0 ton/m 2 /day

The project partners are Celsian (lead investigator), RoMan Manufacturing, TECO, and the Pacific Northwest National Laboratory (PNNL).

600450 Advancing Electric Melting: GMIC’s DOE Grant Progress Update glassonweb.com

See more news about:

Others also read

Maltha Glass Recycling, a leading European recycler and Renewi subsidiary, announces a successful pilot test with Saint-Gobain.
Thomas Wesian, Product Manager at Binder+Co AG, Germany, was a speaker at glass trends live at glasstec 2024, where he spoke about the AI-optimised and data-driven future of recycling.
New production line to drive recycling rates towards 100%
Review of the technical feasibility and sustainability potential of the different end-of-life options for various building glass products
Watch scientists from the EVERGLASS team introduce the project and explain how it is improving the future of glass recycling.
Glass for Europe, FEVE, FERVER, and Kuraray co-publish a joint statement to support the mandatory dismantling of automotive glass in the future EU End-of-Life Vehicles Regulation (ELVR).

Add new comment