Largest End Fired Furnace supplied by HORN – 185.4 m²

Largest End Fired Furnace supplied by HORN – 185.4 m²
Photo source
Horn Glass Industries

Date: 26 June 2024

HORN has completed its biggest End Fired Furnace project in the company´s history with Turkish glass manufacturer Baştürk Cam.

In June 2021, glass melting technology specialist HORN was contracted to build a 560 t/d End Fired Furnace for Bastürk Cam in Malatya, Turkey. The order for Furnace B was placed in 2021, but due to the tragic earthquake in 2023, the project had to be delayed for a while.  

With a melting surface of 185.4 m², the furnace is designed for melting capacity of 560 tpd and includes six forehearths for the production of container glass. Heating of the furnace will be effected by means of Natural Gas or Back-up Diesel oil burners.

In this greenfield project, HORN’s scope of supply included the engineering of the Refractory and Steel structure, the Combustion System, Boosting System, Measuring and Control equipment, a HVR® 600F batch charger (650 tpd. feeding capacity) developed by HORN, NIR Furnace Camera, supervision of erection, heat-up and commissioning.

In June 2024, the new end fired furnace, which produces container glass in the colour Flint, was finally successfully commissioned and on 2nd June 2024 we celebrated the first glass.

To good glass all the time!

Largest End Fired Furnace supplied by HORN – 185.4 m²

Largest End Fired Furnace supplied by HORN – 185.4 m²

Largest End Fired Furnace supplied by HORN – 185.4 m²

Largest End Fired Furnace supplied by HORN – 185.4 m²

600450 Largest End Fired Furnace supplied by HORN – 185.4 m² glassonweb.com

See more news about:

Others also read

Glass Futures announces the appointment of Justin Kelly as new CEO effective 4th November 2024 whilst founding CEO Richard Katz is appointed President.
Şişecam, one of the top five global manufacturers in both glass packaging and flat glass sectors, will participate in the 29th Eurasia Packaging Fair which will take place from October 23-26 at the TÜYAP Fair and Congress Center.
SOTUVER and HORN complete successful cold repair of furnace No. 2 in Tunisia.
Glass furnace manufacturer and turnkey specialist HORN Glass Industries AG was awarded the contract for the general repair of furnace 4 at Noelle + von Campe.
Şişecam has ignited its new glass packaging furnace in Eskişehir and put its glassware furnace into operation after cold repair.
Şişecam, the only global player operating in all core glass areas, participated in the ProWein Fair held in Düsseldorf between March 10-12, 2024.

Add new comment

From industry

NEWS RELATED PRODUCTS